ÇÑ×ÓÊÓƵ High Concrete Repairs at Southwest of Campus

Bond Project ÇÑ×ÓÊÓƵ Charter

 

Start Date: October 15, 2014

Estimated Completion Date: August 28, 2015

 

Project Info: 

  • Project Manager: Anthony Lea; (916) 264-4075 Ext: 3616
  • Architect: HMR
  • Contractor: XL Construction
  • Funding Source: Emergency Repair Program

Construction Description: Concrete repairs in Southwest of campus

 

Project Status:

Last Week (7/7/15):

  • Finish grade

This Week (7/14/15):

  • Concrete forms